外脚手架及卸料平台施工方案-8wr

3.0 2024-11-11 1 0 466.5KB 43 页 3.2金币
侵权投诉
1 编制说明及编制依据........................................................................... 3
1.1 编制说明..............................................................................................................3
1.2编制依据...............................................................................................................3
2 工程概况........................................................................................... 3
3 施工组织........................................................................................... 4
4 施工方法和工艺措施........................................................................... 4
4.1 施工部署.............................................................................................................4
4.2 脚手架搭设.........................................................................................................5
4.3 地基处理.............................................................................................................6
4.4 脚手架及卸料平台设计.....................................................................................6
4.5 脚手架搭设的一般要求......................................................................................8
4.5.1 脚手架搭设顺序............................................................................................8
4.5.2 立杆垫板........................................................................................................8
4.5.3 扫地杆............................................................................................................9
4.5.4 立杆接长........................................................................................................9
4.5.5 杆件位置........................................................................................................9
4.5.6 横向水平杆..................................................................................................10
4.5.7 脚手板..........................................................................................................10
4.5.8 剪刀撑..........................................................................................................10
4.5.9 作业层的栏杆和挡脚板设置......................................................................11
4.5.10 斜道搭设....................................................................................................11
4.5.11 连墙件.....................................................................................................11
4.5.12 门洞处外架搭设.....................................................................................12
4.6 脚手架的拆除....................................................................................................14
4.6.1 准备工作......................................................................................................14
4.6.2 作业程序......................................................................................................14
5 施工质量保证措施............................................................................ 14
6 施工 HSE 保证措施........................................................................... 16
7 双排外脚手架计算书......................................................................... 20
7.1 双排落地式扣件钢管脚手架计算书(按 15M高计算)................................20
7.2 悬挑式扣件钢管脚手架计算书.......................................................................27
7.3 悬挑卸料平台计算书........................................................................................38
1 编制说明及编制依据
1.1 编制说明
为保证本项目施工过程中脚手架搭设、使用、拆除符合有关规范要求,
编制本方案,作为脚手架工程施工的原则性指导文件。
1.2 编制依据
《建筑施工高处作业安全技术规范》(JGJ80-91)
《建筑施工安全检查标准》(JGJ59-99)
《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2001)
《施工现场临时用电安全技术规范》(JGJ 46)
《建筑施工手册》缩印本第四版
新塘组团(一期)还迁住宅 A区工程项目施工图纸
PKPM 施工安全设施计算软件
现场环境和条件。
2 工程概况
本工程由天津滨海金塘建设发展有限公司开发的新塘组团(一期)还迁住
A区工程项目,是多层及高层建筑群的特大工程项目。本工程施工范围包括
桩基工程、基础工程、地下车库、主体结构及建筑工程、室内外给排水、暖通
电气安装工程以及结构内的预留和预埋等。基地位于天津塘沽区腾飞大道南侧。
本项目用地面积约 58985.0m2,形状近似长方形,场地内部地势平坦,室外
±0.000 相当于大沽高3.050m2003 年)。该地区属温带大陆季风性气候,四
季变化明显,平均气温 12 度。主导风向为西南风,年平均风速 4.5M/S
本项目地上部分有 28层住宅(2#4#),12 11 层住宅(1#3#5#
6#7#13#14#15#16#17#18#19#),517 层住宅(8#9#10
#11#12#)以及相应多层配套服务建筑(包括店铺,文化活动站,物业管理
用房,区服务站,居委会街务室,气服务站,
置住宅)。地下部分为一层车库(地下车库层高为 4.2m),中高层住宅地
高为 3.6m面积138233.99m2
建筑面积为 101194.79m2地下建筑面积 37039.2 m2。建筑高度 8层住宅为 24.25
m,11 层住宅建筑高度为 33.6m17 层住宅建筑高度为 51m。住宅层高为 2.9m
墙结构。
3 施工组织
本工程施工组织式,项目理部的管理体设置高、务
摘要:

目录1编制说明及编制依据...........................................................................31.1编制说明..............................................................................................................31.2编制依据..........................................................................................

展开>> 收起<<
外脚手架及卸料平台施工方案-8wr.doc

共43页,预览13页

还剩页未读, 继续阅读

分类:行业资料 价格:3.2金币 属性:43 页 大小:466.5KB 格式:DOC 时间:2024-11-11

开通VIP享超值会员特权

  • 多端同步记录
  • 高速下载文档
  • 免费文档工具
  • 分享文档赚钱
  • 每日登录抽奖
  • 优质衍生服务
/ 43
客服
关注