北京地铁四号线第十七标中关村站基坑回填施工方案

3.0 2024-11-12 1 0 76.5KB 12 页 3.2金币
侵权投诉
中铁二局股份有限公司北京地铁四号线第十七标
........................................................................................................................................................1
1编制依据.................................................................................................................................................2
2工程概况.................................................................................................................................................2
2.1 工程地理位置及周边环境.............................................................................................................2
2.2 设计概况.........................................................................................................................................2
2.3 基坑回填工程重点难点.................................................................................................................2
3、施工安排.............................................................................................................................................2
3.1、工期安排......................................................................................................................................2
3.2 劳动组织及责任分工.....................................................................................................................2
3.2.1 管理层负责人..............................................................................................................................3
4、施工准备.............................................................................................................................................3
4.1、技术准备......................................................................................................................................3
4.2、机械设备配备..............................................................................................................................3
4.3、材料准备......................................................................................................................................4
5、主要施工方法.....................................................................................................................................4
5.1、工艺流程......................................................................................................................................4
5.2、操作工艺......................................................................................................................................4
5.21、基底清理....................................................................................................................................4
5.2.2、检验土质...................................................................................................................................4
5.2.3、分层铺摊填土...........................................................................................................................4
5.2.4、分层碾压.................................................................................................................................5
5.3、检验密实度.................................................................................................................................5
6质量要求.................................................................................................................................................6
7、环境、职业健康安全文明施工措施.................................................................................................6
7.1、环境文明施工措施.....................................................................................................................6
7.2、职业健康安全管理措施.............................................................................................................7
1
中铁二局股份有限公司北京地铁四号线第十七标
中关村站基坑回填施工方案
1编制依据
1.1中关村站主体结构施工图(A版)(BJ4——11—SS——04
1.2《路基工程施工质量验收标准>>( QGD—010—2005)
1.3
2 工程概况
2.1 工程地理位置及周边环境
中关村站位于中关村大街与北四环路交叉十字路口南侧,中关村大街下方
呈南北走向,场区周围为电子、电脑商城等高层建筑,商业发达。中关村大街
及北四环路下方管线重多,涉及电力、电信、热力、上水、天然气、污水、雨
水等。
2.2 设计概况
179.9m
22.5m,顶板埋深约 2.5 m3.0m
2.3 基坑回填工程重难点
1.基坑施工范围位于中关村大街主路,基坑边距主路较近,保证主路交
通安全,为施工重点。
2.基坑内存在纵贯基坑南北及东西的电信管沟,在基坑回填压实过程中
2
中铁二局股份有限公司北京地铁四号线第十七标
保证电信管沟两侧回填土压实度难度较高。
3、施工场地本已狭小,且存在电信管沟加剧了场地的狭小,致使施工过
程中各种工序间相互干扰,从而降低各种施工机械效率的正常发挥,如何协调
成为难点。
4、该基坑位于中关村大街主路上,对基坑回填土压实度要求较高。
3、施工安排
3.1、工期安排
顶板回填 40 2007.2.26 2007.4. 6
1.1
电信管沟施工 18 2007.2.26 2007.3.15
1.2
顶板土方回填 7 2007.3.16 2007.3.23
1.3
三期交通道改及管线改移 15 2007.3.24 2007.4.6
3.2 劳动组织及责任分工
3.2.1 管理层负责人
为了保证整个工程的施工质量,经理部组织了有经验的管理人员进行施工
管理。
3
项目经理
李斌成
总工程师
方朝刚
工程部
赵大兵
质检部
张洪锁
物资部
周 建
安质部
王德祥
施工队领工员
杨凤
摘要:

中铁二局股份有限公司北京地铁四号线第十七标目录目录........................................................................................................................................................11编制依据........................................................................................................................

展开>> 收起<<
北京地铁四号线第十七标中关村站基坑回填施工方案.doc

共12页,预览4页

还剩页未读, 继续阅读

分类:行业资料 价格:3.2金币 属性:12 页 大小:76.5KB 格式:DOC 时间:2024-11-12

开通VIP享超值会员特权

  • 多端同步记录
  • 高速下载文档
  • 免费文档工具
  • 分享文档赚钱
  • 每日登录抽奖
  • 优质衍生服务
/ 12
客服
关注